A malfunction within the cooling system at the second of two additional nuclear reactors at Plant Vogtle is forcing Georgia Power to delay the unit’s in-service date until the second quarter of this year.

ATLANTA — The first of two new nuclear reactors being built at Georgia Power’s Plant Vogtle likely won’t go into service this November as planned, the Atlanta-based utility announced Friday.

The project could be delayed by one month or more at a cost of about $25 million for each month, Georgia Power disclosed in a filing with the U.S. Securities and Exchange Commission.

Recommended for you

(0) comments

Welcome to the discussion.

Please log in, or sign up for a new, free account to read or post comments.

Keep it Clean. Please avoid obscene, vulgar, lewd, racist or sexually-oriented language.
PLEASE TURN OFF YOUR CAPS LOCK.
Don't Threaten. Threats of harming another person will not be tolerated.
Be Truthful. Don't knowingly lie about anyone or anything.
Be Nice. No racism, sexism or any sort of -ism that is degrading to another person.
Be Proactive. Use the 'Report' link on each comment to let us know of abusive posts.
Share with Us. We'd love to hear eyewitness accounts, the history behind an article.